Solar · United Kingdom
Bentley Motors
Operator Bentley Motors
Operational2.9 MWData checked 16 November 2026Source record dated 28 January 2019
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Bentley Motors is a 2.9 MW solar farm on the edge of Crewe, Cheshire, United Kingdom. Its planning application (16/4268N) went to Cheshire East on 31 August 2016 and was granted on 24 November 2016. It has been operating since 1 August 2018. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 34 other energy sites within 10 km, 28 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.
Get an email when Bentley Motors changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, solar PV incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every solar incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Solar
- Capacity
- 2.9 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- Bentley Motors
- Location
- Bentley Motors Ltd, Pyms Lane, Crewe, Cheshire, CW1 3PL, United Kingdom
- Planning authority
- Cheshire East
- Planning application
- 16/4268N
- First operating
- 2018
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 16/4268N, with what the planning evidence pack adds for this site.
Every application in Cheshire East · Alerts for applications and incidents near here
Timeline
- 31 August 2016 Planning application submitted
- 24 November 2016 Planning permission granted
- 21 March 2018 Construction started
- 1 August 2018 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Bentley Motors. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Bentley Motors had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Bentley Motors; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
- What is the status of Bentley Motors?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 28 January 2019.
- Where is Bentley Motors?
- On the edge of Crewe, Cheshire, United Kingdom (postcode CW1 3PL).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).