← Back to Cheshire

Solar · United Kingdom

Bentley Motors Ltd 1

Operator Bentley Motor Cars Ltd

Operational5.1 MWData checked 16 November 2026Source record dated 15 April 2013

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Bentley Motors Ltd 1 is a 5.1 MW solar farm on the edge of Crewe, Cheshire, United Kingdom. Its planning application (11/1042N) went to Cheshire East on 14 March 2011 and was granted on 8 June 2011. It has been operating since 21 March 2013. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 33 other energy sites within 10 km, 27 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

459 energy sites within 40 km for Bentley Motors Ltd 1

Members see the sites and incidents around this one, and every record behind them.

Technology
Solar
Capacity
5.1 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Bentley Motor Cars Ltd
Location
Pyms Lane, Crewe, Cheshire, CW1 3PL, Cheshire, United Kingdom
Planning authority
Cheshire East
Planning application
11/1042N
First operating
2013

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 11/1042N, with what the planning evidence pack adds for this site.

Every application in Cheshire East · Alerts for applications and incidents near here

  • 14 March 2011 Planning application submitted
  • 8 June 2011 Planning permission granted
  • 15 December 2012 Construction started
  • 21 March 2013 Operational

None found. The register holds no published incident that names Bentley Motors Ltd 1. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Bentley Motors Ltd 1 had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Bentley Motors Ltd 1; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Bentley Motors Ltd 1?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 15 April 2013.
Where is Bentley Motors Ltd 1?
On the edge of Crewe, Cheshire, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).