Algoma Steel Group, based in Sault Ste. Marie, Ontario, reported an unplanned outage at its Lake Superior Power generating facility. One turbine unit detected an abnormal condition and went offline. The company said the remaining units were unaffected....
GE Vernova
Named in a role in 16 records, between 2019 and 2026.
Being named is not a finding of fault. Counts are of records in published reporting, not rates, and the company's role is the one the sources give.
Company history. GE Vernova was spun off from General Electric on 2 April 2024. Incidents before then may name GE, and are on its page. See GE. Source: GE Vernova, 2 April 2024.
Work at GE Vernova? See every record that names it, free, and ask for a correction or add your side.
Records naming this company
Free entries that mention GE Vernova
Reporting states that three men broke into a GE Vernova wind turbine in Spain and that one of them was fatally electrocuted. The Spanish Civil Guard inspected the turbine where the incident took place. Arrests have been reported in connection with the death....
At approximately 5:03pm on a Saturday evening, the hub of a wind turbine at the 99MW Erie Shores Wind Farm in Ontario detached from the tower and fell to the ground with all three blades still attached. The site, owned and operated by Capstone Infrastructure,...
See what failed, why, and what it cost
The record behind each entry: the manufacturer, integrator and operator, root cause, failure mode, downtime, losses and every source.
On 27 February 2025, a GE Vernova Haliade-X 13 MW turbine (AW-38) at the Vineyard Wind 1 offshore wind farm off Massachusetts was struck by lightning. The turbine had previously suffered a blade failure in July 2024, when a blade detached and debris washed up...
Two wind turbine maintenance technicians fell to their deaths on Saturday 22 February 2025 while working at the Plum Creek Wind Farm near Winside, Wayne County, Nebraska. The local sheriff's office said the men, part of a wind turbine maintenance crew, had...
On the morning of 22 August 2024 a blade failure occurred on a large multi-megawatt turbine at Dogger Bank A, an offshore wind farm under construction in the North Sea, United Kingdom. It was the second blade failure at the same project in 2024, following an...
In July 2024, a recently installed turbine at the Vineyard Wind 1 offshore wind project, located south of Martha's Vineyard and Nantucket, Massachusetts, United States, suffered a blade failure during early testing. The turbine had been running for about six...
In May 2024, a blade on an installed turbine at Dogger Bank A, an offshore wind farm under construction in the North Sea off the coast of England, United Kingdom, sustained damage. The Dogger Bank Wind Farm consortium, the project's owner and operator,...
A published report says a GE Vernova wind turbine collapsed at a 75MW wind farm in Lithuania, leaving the farm with lost production. The farm is reported to use turbines from GE's 5.X platform. A Lithuanian state-owned renewables developer is reported to be...
A worker died after becoming trapped between an elevator and the shaft inside a GE Vernova wind turbine at the Markbygden wind complex in Sweden. The incident occurred the previous year relative to the report. Following an investigation, authorities decided...
On 3 September 2021, Recharge reported a blade failure that damaged a 5.3MW GE Vernova onshore turbine at Björkvattnet in northern Sweden. The manufacturer was analysing the root cause. Injuries, the extent of damage beyond the blade, and whether the turbine...
What this page is, and what it is not
It counts the records in this register that name this company in any role. Being named is not a finding of fault. Most incidents have several contributing causes, and the company named as manufacturer, integrator, operator or contractor is often not the cause of what went wrong.
Counts reflect what public reporting names, so a company with a large installed base, or one operating where reporting is open, will appear more often than a company of the same size elsewhere. Read the counts alongside the note on coverage in the methodology.
If you work for this company and something here is wrong, tell us and we will correct it. Use the corrections page: we acknowledge within 2 working days and decide within 10.