Thompson House Equestrian farm

Operational5 MWApplication A/14/79904/MAJORSubmitted 13 October 2014Granted 6 February 2015

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
A/14/79904/MAJOR
Planning authority
Wigan
County or area
Greater Manchester
Nation
England
Technology
Solar
Capacity
5 MW
Status
Operational
Operator or applicant
Emotion Solar One
Location
Thompson House Equestrain Centre, Pepper Lane, Standish, WN6 0PP
First operating
2016
  • 13 October 2014 Planning application submitted
  • 6 February 2015 Planning permission granted
  • 5 January 2016 Construction started
  • 31 March 2016 Operational

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1244, Fire reported to have started in solar panels at Westleigh primary school, 16 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-12442018Fire reported to have started in solar panels at Westleigh primary school16 kmSignificant
EIR-14852026Faulty solar panel wiring sparks house fire in Stoke-on-Trent68 kmMinor
EIR-15462025Solar panel isolation switch overheats in roof fire at a house in Bucknall73 kmMinor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near WN6 0PP is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Wigan.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.