Planning application · Onshore wind · Newark and Sherwood

Stonish Hill (Bilsthorpe)

Operational10.3 MWApplication 07/00856/FULEIASubmitted 8 June 2007Granted on appeal 16 March 2009

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
07/00856/FULEIA
Planning authority
Newark and Sherwood
County or area
Nottinghamshire
Nation
England
Technology
Onshore wind
Capacity
10.3 MW
Status
Operational
Operator or applicant
REG Power Management (John Laing/Peel Energy)
Location
Former Bilsthorpe Colliery Eakring Road Bilsthorpe
Appeal reference
APP/B3030/A/08/2072487/NWF
Turbines
5
First operating
2013
  • 8 June 2007 Planning application submitted
  • 6 March 2008 Planning permission refused
  • 16 March 2009 Planning permission granted
  • 16 March 2009 Appeal granted
  • 25 June 2012 Construction started
  • 31 March 2013 Operational

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0923, Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure, 79 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-09232009Wind turbine blade detaches at Conisholme wind farm in Lincolnshire after bolt failure79 kmSignificant
EIR-19462022Wind turbine fire sends black smoke across Hull82 kmSignificant
EIR-18102022Wind turbine at Cargill Hull factory damaged by fire82 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Stonish Hill (Bilsthorpe) is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Newark and Sherwood.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.