Spring Farm Ridge

Application Refused15 MWApplication S/2010/1437/MAFSubmitted 19 October 2010Refused by the Secretary of State 23 December 2014

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
S/2010/1437/MAF
Planning authority
West Northamptonshire
County or area
Northamptonshire
Nation
England
Technology
Onshore wind
Capacity
15 MW
Status
Application Refused (Secretary of State - Refusal)
Operator or applicant
Broadview Energy
Location
land to the north of Welsh Lane between Greatworth and Helmdon
Appeal reference
APP/Z2830/A/11/2165035/NWF
Turbines
5
  • 19 October 2010 Planning application submitted
  • 30 June 2011 Planning permission refused
  • 11 April 2013 Appeal lodged
  • 23 December 2014 Refused by the Secretary of State
  • 23 December 2014 Appeal refused

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1578, Wind turbine fire near Chumleigh in Devon, 81 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-15782024Wind turbine fire near Chumleigh in Devon81 kmSignificant
EIR-12752022Fire damages Siemens Gamesa turbine at French Farm wind farm83 kmSignificant
EIR-20212022Wind turbine catches fire near Thorney in Lincolnshire93 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Spring Farm Ridge is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in West Northamptonshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.