← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · South Hams

Riverford Farm

Planning Permission Expired49.9 MWApplication 3360/17/FULSubmitted 18 October 2017Granted 4 December 2017

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
3360/17/FUL
Planning authority
South Hams
County or area
Devon
Nation
England
Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Planning Permission Expired
Operator or applicant
Abham Storage / Statera Energy
Location
Riverford Farm, Zc88 at A384 to Staverton Brid, Staverton, Totnes, Devon, TQ9 6AF
  • 18 October 2017 Planning application submitted
  • 4 December 2017 Planning permission granted
  • 5 January 2021 Planning permission expired

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0249, Smoke and fire incident at Battery Box, Pinhoe Road, Exeter, 36 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-02492026Smoke and fire incident at Battery Box, Pinhoe Road, Exeter36 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire188 kmSignificant
EIR-01092025Fire in single battery unit at Thurrock BESS under construction312 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near TQ9 6AF is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in South Hams.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.