← Back to Devon

Energy sites / United Kingdom / Devon

Battery storage · United Kingdom

Riverford Farm

Planning Permission Expired49.9 MWChecked 6 October 2026Last changed in the dataset 21 August 2020

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Planning Permission Expired
Operator or applicant
Abham Storage / Statera Energy
Location
Riverford Farm, Zc88 at A384 to Staverton Brid, Staverton, Totnes, Devon, Devon, TQ9 6AF, United Kingdom
Planning authority
South Hams
Planning application
3360/17/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 18 October 2017 Planning application submitted
  • 4 December 2017 Planning permission granted
  • 5 January 2021 Planning permission expired

None found. The register holds no published incident that names Riverford Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.