Llanwern Solar Farm & Battery Storage

Operational75 MWApplication DNS/3213968Submitted 20 February 2018Granted 13 November 2018

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
DNS/3213968
Planning authority
Welsh Government (NSIP)
County or area
Gwent
Nation
Wales
Technology
Solar
Capacity
75 MW
Status
Operational
Operator or applicant
NextEnergy Capital LLP
Location
S/o Whitson Electricity Substa, Broad Street Common, Nash, Newport, NP18 2BE
First operating
2021
  • 20 February 2018 Planning application submitted
  • 13 November 2018 Planning permission granted
  • 1 June 2020 Construction started
  • 1 March 2021 Operational

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1416, Fire at Bristol hospital started in solar panels, 26 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-14162025Fire at Bristol hospital started in solar panels26 kmSignificant
EIR-12742022Fire damages rooftop solar panels at We The Curious in Bristol26 kmSignificant
EIR-20652021Loft fire believed caused by a solar panel at Paintworks flats in Bristol27 kmMinor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near NP18 2BE is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Welsh Government (NSIP).

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.