Full planning pack, launch price £145Other options

Planning application · Battery storage · Wakefield

Kirkhaw Lane - Battery Storage Energy

Operational150 MWApplication 21/02758/CPLSubmitted 11 November 2021Granted 6 June 2023

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
21/02758/CPL
Planning authority
Wakefield
County or area
West Yorkshire
Nation
England
Technology
Battery storage (Stand-alone Storage)
Capacity
150 MW
Status
Operational
Operator or applicant
SSE Enterprise Contracting
Location
Ferrybridge Power Station, Kirkhaw Lane, Knottingley, WF11 8RB
First operating
2026
  • 11 November 2021 Planning application submitted
  • 6 June 2023 Planning permission granted
  • 23 March 2026 Operational

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0584, Fire in a battery container at Rufford Colliery BESS, Rainworth, caused by a short circuit in NMC cells, 68 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth, caused by a short circuit in NMC cells68 kmSignificant
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool114 kmMajor
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire227 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near WF11 8RB is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Wakefield.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.