← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Battery storage · Perth and Kinross

Cordon Farm, Abernethy - Battery Storage

Refused30 MWApplication 24/01558/FLMSubmitted 30 October 2024Refused 18 August 2026

Status as recorded in the register on 3 August 2026: Application Submitted

Newer official status: Refused by the Scottish Ministers on 18 August 2026 (source: Scottish Government planning appeals (DPEA), case NA-340-008, checked 9 Oct 2026)

Perth and Kinross Council's planning committee resolved to approve the application on 3 September 2025. The Scottish Ministers then called it in (case NA-340-008) and refused planning consent on 18 August 2026.

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
24/01558/FLM
Planning authority
Perth and Kinross
County or area
Tayside
Nation
Scotland
Technology
Battery storage (Stand-alone Storage)
Capacity
30 MW
Status
Refused by the Scottish Ministers (newer official status; the register records Application Submitted)
Operator or applicant
Elgin Energy EsCo Limited
Location
600 Metres North East Of Cordon Farm Abernethy, PH2 9LN
  • 30 October 2024 Planning application submitted
  • 18 August 2026 Planning permission refused

The pack for this site lists 5 comparable battery incidents in the United Kingdom, grid-scale only, nearest first. The nearest is EIR-0638, Explosion and prolonged fire at Orsted battery storage site in Liverpool, 329 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-06382020Explosion and prolonged fire at Orsted battery storage site in Liverpool329 kmMajor
EIR-05842026Fire in a battery container at Rufford Colliery BESS, Rainworth, caused by a short circuit in NMC cells385 kmSignificant
EIR-00582025Fire in two battery containers at Cirencester Hybrid Solar Farm, Gloucestershire523 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 2 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near PH2 9LN is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Perth and Kinross.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.