Full planning pack, launch price £145Other options

Planning application · Onshore wind · Burnley

Coal Clough Wind Farm Repowering

Operational16 MWApplication APP/2009/0758Submitted 22 December 2009Granted 21 January 2013

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
APP/2009/0758
Planning authority
Burnley
County or area
Lancashire
Nation
England
Technology
Onshore wind
Capacity
16 MW
Status
Operational
Operator or applicant
Coal Clough Wind Farm
Location
Coal Clough Wind Farm,The Long Causeway, Burnley
Turbines
8
First operating
2015
  • 22 December 2009 Planning application submitted
  • 21 January 2013 Planning permission granted
  • 14 May 2014 Construction started
  • 1 May 2015 Operational

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1624, Crane topples on Scout Moor wind farm project, 30 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-16242026Crane topples on Scout Moor wind farm project30 kmMajor
EIR-07322026Nordex turbine damaged by suspected lightning strike at UK wind farm33 kmMinor
EIR-08632017Fire destroys single turbine at Knabs Ridge wind farm near Harrogate48 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Coal Clough Wind Farm Repowering is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Burnley.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.