Accra power outages blamed on transformer faults and upgrades
2026Published 26 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in Ghana, and an email when EIR-3055 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Electricity Company of Ghana
What happened
The Electricity Company of Ghana (ECG) attributed power outages affecting several communities in Accra over the preceding two weeks to a mix of planned transformer upgrades and replacement works and emergency faults on its distribution network. The planned works were under way in parts of Accra East and Accra West, including Kwabenya, Adenta, Boteyman, Teshie and Dodowa. ECG said some outages were not linked to the planned maintenance but stemmed from emergency faults, including overloaded transformers and problems with the distribution network.
One cited emergency fault was an underground cable fault at Ashongman Villa, which affected supply to the Atomic Hospital area, Atomic Theatre site, Ashongman Veggies, Ashongman Mangoase, Ashongman Estate and adjoining communities. Residents experienced intermittent electricity supply. ECG apologised to affected customers for the inconvenience.
Contributing factors
ECG cited overloaded transformers, problems with the distribution network and an underground cable fault at Ashongman Villa. ECG said completion of the Katamanso substation would help ease supply challenges in the affected communities. No independent investigation of the causes is reported.
Lessons learned
- Give customers clear notice of planned transformer works and distinguish planned outages from emergency faults in public communications.
- Monitor transformer loading and act before overload, since overloaded transformers were cited as a cause of emergency outages.
- Keep accurate records of underground cable routes and inspect them regularly so that faults can be located and repaired quickly.
More lessons on outages, backup supply and restoration, detection and monitoring, electrical protection and isolation, from every incident on the register.