Transformer fire at Apo transmission substation in Abuja, Nigeria

Apr 2019Published 19 Nov 2026Responsible editor: Chief Editor

Estimated damageEstimated by the register's adjusterHow? Know the real figure?
Figure hidden: shown to subscribersMedium confidence
supply cut for about •• daysShown in the record →Full estimate
From the recordRoot cause hiddenFailed part hidden

Companies named in the reporting of this entry (being named is not a finding of fault): Transmission Company of Nigeria

On Sunday 28 April 2019, a fire broke out at about 13:33 at the Apo transmission substation in Abuja, operated by the Transmission Company of Nigeria (TCN). The fire involved one of the substation's 45MVA 132/33kV power transformers, which was feeding 33kV feeders supplying the Abuja Electricity Distribution Company (AEDC). TCN stated that the fire resulted from a direct fault on one of AEDC's 33kV feeders, which had a history of repeated tripping and lacked protection.

TCN also stated that the 33kV feeder H13 circuit breaker and current transformer exploded and the outgoing 33kV connection to the transformer snapped, causing the fire. Federal, FCT and NNPC fire services put the fire out. TCN later reported that normal transmission had been restored through the substation and that the 26MW load from the burnt transformer had been moved to a 100MVA transformer. TCN said that supply to areas taking power through AEDC would not be affected, because the substation has N-1 redundancy. At the time of the statement, TCN had not determined whether the burnt transformer could be salvaged.

TCN stated that the fire was caused by a direct fault on an AEDC 33kV feeder with a history of tripping and no protection on the 33kV line. TCN is also investigating a possible protection failure on its 45MVA power transformer.

  1. Feeders connected to transmission substations need protection that is maintained and coordinated, so that a fault is cleared before it damages a transformer.
  2. Repeated tripping of a feeder is a warning sign that should prompt investigation and remedial work before a fault causes a fire.
  3. N-1 redundancy and the ability to transfer load to other transformers can limit customer impact from an equipment fire, but the failed unit still needs a formal assessment for salvage.

More lessons on electrical protection and isolation, outages, backup supply and restoration, from every incident on the register.

Published 2026-11-19. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Grid infrastructure incidents in Nigeria, by year, free with a credit (PNG).

Grid infrastructure incidents in Nigeria: 22 entries, with a free alert for the next one.

Substation and transformer fires: the counts, the latest entries and a free alert for the next one. Also: transformer explosions and switchgear and breaker fires.

Browse the full register or submit an incident.