Transformer fire delays Watts Bar Unit 2 commissioning
Aug 2016Published 5 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in the United States, and an email when EIR-2023 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Tennessee Valley Authority
What happened
On 30 August 2016, an electrical fault on the 2B main bank transformer at Tennessee Valley Authority's Watts Bar Unit 2 caused the main turbine to trip. The reactor also tripped by design. The fault led to an oil fire in an exterior switchyard transformer, reported about a minute later and extinguished by the onsite emergency response team. The unit was in power ascension testing and had reached 99% power the previous day.
The operator said the incident was likely to keep commercial operation from the then end-of-summer target, and that testing could not continue until the transformer was restored or another path to the switchyard was established. No timetable was given.
Contributing factors
The source reports an electrical fault on the 2B main bank transformer as the initiating event. It does not state a deeper cause. The installed transformer was not new: it had been on site since the 1990s, had been modified and maintained, and had previously been used on Unit 1. Damage had not been fully diagnosed, and it was not yet decided whether to repair or replace it. A spare transformer was on site.
Lessons learned
- During commissioning, a single main transformer fault can stop power ascension and push back commercial operation, so spare equipment or an alternative path from the generator to the switchyard should be identified in advance.
- Do not treat a long-service transformer as proven for a new unit solely because it has been modified, maintained or used elsewhere; diagnose damage before choosing repair or replacement.
- Practised onsite response can limit a switchyard oil fire before it develops into a wider event.
More lessons on design, standards and commissioning, maintenance, inspection and ageing assets, from every incident on the register.
Source
Other entries that name Watts
Published 2026-10-05. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.