Transformer fires trigger emergency shutdown at Waterford 3 nuclear plant
Mar 2024Published 1 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in the United States, and an email when EIR-1730 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Entergy
What happened
Two transformers caught fire in the main transformer yard at Entergy's Waterford 3 nuclear generating plant in Killona. According to the Nuclear Regulatory Commission, the fires led to an emergency SCRAM, a rapid shutdown of the reactor by insertion of its control rods, and the plant's emergency director declared an unusual event, the lowest emergency classification, at 12:09 a.m. on a Friday. A local fire department responded, but the plant's own fire brigade put the fire out.
The unusual event ended at 2:21 a.m. after the fire was extinguished. The generator had not restarted at the time of reporting, and Entergy said the related work should take several weeks. Plant officials notified the Federal Emergency Management Agency and Louisiana emergency officials. The NRC said the fire was contained on site, there was no danger of a radiation release, and no public notification was required because the event did not pose a threat to public health and safety.
Contributing factors
The source does not report why the transformers caught fire.
Lessons learned
- Keep an on-site fire brigade able to extinguish electrical fires in a main transformer yard, including when an outside fire service also responds.
- For a low-level nuclear emergency, record clearly which regulators and emergency officials were notified and why no public warning was required.
- Plan for the plant to remain in a safe shutdown for several weeks while main-yard transformer repairs are scheduled.
More lessons on fire suppression and firefighting, emergency response and public communication, from every incident on the register.
Source
Site page: Waterford Substation (status, dates and other incidents)
Published 2026-10-01. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.