Smoke and a reported fire at Bicchu Hirose substation in Takahashi suspend rail services

May 2026Published 30 Sept 2026Responsible editor: Chief Editor

Estimated damageEstimated by the register's adjusterHow? Know the real figure?
Figure hidden: shown to subscribersLow confidence
supply cut for about •• daysShown in the record →Full estimate
From the recordRoot cause hiddenFailed part hidden

Smoke was reported at the Bicchu Hirose substation in Takahashi City at about 05:20 on 28 May 2026. A newspaper headline reported a fire at the substation. Services on the Hakubi Line were suspended for about half a day. A tree had fallen onto overhead lines between Hokoku and Ikura, and reports said this may have been the cause. The extent of any fire, injuries, and the link between the line damage and the substation are not stated in the available captions.

A fallen tree damaging overhead lines is reported as a possible cause. No confirmed cause is given.

  1. Vegetation near overhead lines can damage equipment and interrupt supply.
  2. A line fault may affect a substation, so isolation and restoration plans should be ready.
  3. Early reports may confirm smoke and service impact before the cause is known.

More lessons on outages, backup supply and restoration, electrical protection and isolation, emergency response and public communication, from every incident on the register.

Published 2026-09-30. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Grid infrastructure incidents by year, free with a credit (PNG).

Grid infrastructure incidents in Japan: 4 entries, with a free alert for the next one.

Substation and transformer fires: the counts, the latest entries and a free alert for the next one. Also: power line and cable failures.

Browse the full register or submit an incident.