Veld fires trip Sebenza substation causing Johannesburg outages
Aug 2024Published 29 Sept 2026
Companies named in this entry: City Power
What happened
On 19 August 2024 City Power reported that the Sebenza Substation tripped because of veld fires. The outage affected customers in parts of Alexandra, the inner city, Midrand and areas served by the Reuven Service Delivery Centre. Johannesburg Emergency Services attended to extinguish the fire beneath the transmission station. City Power operators were dispatched to restore supply once the fire was contained. The duration of the outage was not confirmed at the time of the announcement. City Power advised that regular updates would be issued to customers and cautioned residents against actions that contribute to veld fires. The company apologised for the inconvenience caused.
Contributing factors
Veld fires in the vicinity of the substation.
Lessons learned
- Maintain regular vegetation management around substation perimeters to reduce external fire exposure.
- Establish rapid response protocols with local emergency services for fire events near grid assets.
- Provide timely public updates during outages to minimise customer impact.
Source
Published 2026-09-29. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.