Fire reported at a 66 kV substation in Ludhiana
Dec 2024Published 29 Sept 2026
What happened
A fire, described in reporting as massive, was reported at a 66 kV substation in Ludhiana on 12 December 2024. A director of PSPCL was reported to have visited the site to oversee restoration. PSPCL was quoted as saying it was committed to minimising disruptions and addressing the situation swiftly. The cause, the extent of damage, any injuries and the effect on supply were not reported in the source available to the register.
Contributing factors
The source does not report a cause or any contributing factor.
Lessons learned
- A substation fire should trigger an early check of supply impact and a clear restoration plan once the site is safe.
- Early reports often omit cause and damage, so operators should confirm what failed before drawing conclusions.
- Keep a record of the equipment involved, the response and the restoration steps for later review.
Source
Published 2026-09-29. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.