Fatal wind turbine blade failure at Araya Seaside Park, Akita, Japan
May 2025Published 15 Sept 2026Responsible editor: Chief Editor
- Where
- Araya Seaside Park, Akita prefecture, Japan
- Manufacturer
- Enercon
- What
- 40-metre blade broke off wind turbine
- Injuries
- 81-year-old man died from head injuries
- Cause
- Under investigation
Get the next one by email
Free alerts on wind (onshore) incidents in Japan, and an email when EIR-0748 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Enercon
What happened
An 81-year-old man died after a 40-metre wind turbine blade broke off and fell to the ground at Araya Seaside Park in Akita prefecture, Japan. Police received an emergency call on the Friday morning reporting that a blade had broken off a turbine at the park. A local meteorological observatory had issued a strong wind warning for the city that morning. The man was found lying unconscious with head injuries about a metre from the fallen blade and was later pronounced dead in hospital.
Local police opened an investigation into the cause. The turbine involved was an Enercon E-82, which Enercon said was operated and serviced by a local partner. Enercon confirmed it was bringing forward regularly scheduled blade inspections at other wind farms in Japan using the same turbine type while the cause is investigated.
Contributing factors
A strong wind warning had been issued for the city on the morning of the incident. The mechanical cause of the blade detachment had not been determined at the time of reporting and is under investigation by local police, with the manufacturer supporting the inquiry.
Lessons learned
- Operators of Enercon E-82 turbines should bring forward blade inspections across the fleet after one blade detaches.
- Public exclusion zones around turbines must be enlarged or access closed during strong wind warnings.
- Local operating partners must enable rapid manufacturer support to police investigations of blade failures.
More lessons on structural integrity and turbines, emergency response and public communication, from every incident on the register.
Not yet known
- Mechanical cause of the blade detachment
- Age and service history of the turbine
- Cost of repairs and lost generation
- Duration of any site shutdown