Solar · United Kingdom

York Solar Farm

Operator Gridserve · Owner Warrington Renewables (York) LTD

Operational34.7 MWData checked 16 November 2026Source record dated 28 May 2020

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

York Solar Farm is a 34.7 MW solar farm 12 km south-east of Thirsk, North Yorkshire, United Kingdom. Its planning application (15/01268/FUL) went to North Yorkshire on 5 June 2015 and was granted on 21 September 2015. It has been operating since 18 December 2019. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 14 other energy sites within 10 km, 10 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

The operator's 2 other sites and 202 energy sites within 40 km for York Solar Farm

Members see the sites and incidents around this one, and every record behind them.

Technology
Solar
Capacity
34.7 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Gridserve
Owner
Warrington Renewables (York) LTD
Location
Boscar Grange Farm, Thirsk Road, Easingwold, York, North Yorkshire, North Yorkshire, YO61 3NQ, United Kingdom
Planning authority
North Yorkshire
Planning application
15/01268/FUL
First operating
2019

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 15/01268/FUL, with what the planning evidence pack adds for this site.

Every application in North Yorkshire · Alerts for applications and incidents near here

  • 5 June 2015 Planning application submitted
  • 21 September 2015 Planning permission granted
  • 23 May 2019 Construction started
  • 18 December 2019 Operational

None found. The register holds no published incident that names York Solar Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has York Solar Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names York Solar Farm; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of York Solar Farm?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 28 May 2020.
Where is York Solar Farm?
12 km south-east of Thirsk, North Yorkshire, United Kingdom (postcode YO61 3NQ).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).