Operational5 MWChecked 6 October 2026Last changed in the dataset 18 April 2019

Technology
Solar
Capacity
5 MW
Status
Operational
Operator or applicant
S4N Worsted/
Location
Land At Worsted Farm, Worsted Lane, East Grinstead, West Sussex, West Sussex, RH19 3UF, United Kingdom
Planning authority
Mid Sussex
Planning application
DM/15/3056
Appeal reference
APP/D3830/W/16/3151730
First operating
2019

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 15 September 2015 Planning application submitted
  • 24 December 2015 Planning permission refused
  • 27 June 2016 Appeal lodged
  • 21 November 2016 Planning permission granted
  • 21 November 2016 Appeal granted
  • 1 January 2019 Construction started
  • 16 April 2019 Operational

None found. The register holds no published incident that names Worsted Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.