← Back to Kent

Solar · United Kingdom

Tonge Corner Farm

Operator Martifer Solar (Voltalia)

Operational22 MWData checked 16 November 2026Source record dated 24 August 2016

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Tonge Corner Farm is a 22 MW solar farm 3.7 km north-east of Sittingbourne, Kent, United Kingdom. Its planning application (SW/14/0224) went to Swale on 11 March 2014 and was granted on 28 August 2015. It has been operating since 30 March 2016. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 52 other energy sites within 10 km, 31 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

The operator's 2 other sites and 481 energy sites within 40 km for Tonge Corner Farm

Members see the sites and incidents around this one, and every record behind them.

Technology
Solar
Capacity
22 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Martifer Solar (Voltalia)
Location
Land North and West of Tonge Corner Farm, Tonge Corner Road, Tonge, Sittingbourne, Kent, Kent, ME9 9BB, United Kingdom
Planning authority
Swale
Planning application
SW/14/0224
First operating
2016

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for SW/14/0224, with what the planning evidence pack adds for this site.

Every application in Swale · Alerts for applications and incidents near here

  • 11 March 2014 Planning application submitted
  • 28 August 2015 Planning permission granted
  • 20 January 2016 Construction started
  • 30 March 2016 Operational

None found. The register holds no published incident that names Tonge Corner Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Tonge Corner Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Tonge Corner Farm; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Tonge Corner Farm?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 24 August 2016.
Where is Tonge Corner Farm?
3.7 km north-east of Sittingbourne, Kent, United Kingdom (postcode ME9 9BB).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).