← Back to Kent

Energy sites / United Kingdom / Kent

Battery storage · United Kingdom

Plot 2B EurolinkV

Under Construction20 MWChecked 6 October 2026Last changed in the dataset 13 December 2021

Technology
Battery storage (Stand-alone Storage)
Capacity
20 MW
Status
Under Construction
Operator or applicant
Trenport Investments
Location
Plot 2B Eurolink V, Sittingbourne, Land orth of Swale Way, Sittingbourne, Kent, ME9 9AR, United Kingdom
Planning authority
Swale
Planning application
19/502257/FULL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 3 May 2019 Planning application submitted
  • 25 July 2019 Planning permission granted
  • 1 October 2021 Construction started
  • 25 October 2022 Planning permission expired

None found. The register holds no published incident that names Plot 2B EurolinkV. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.