← Back to Derbyshire

Energy sites / United Kingdom / Derbyshire

Battery storage · United Kingdom

The Electricity Substation, Baslow Road - Energy Storage System

Application Refused0.2 MWChecked 6 October 2026Last changed in the dataset 9 December 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
0.2 MW
Status
Application Refused (Planning Permission Refused)
Operator or applicant
AMP Clean Energy
Location
N/O The Electricity Substation, Baslow Road, Holymoorside, Chesterfield, Derbyshire, S42 7BN, United Kingdom
Planning authority
North East Derbyshire
Planning application
25/00649/FL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 13 August 2025 Planning application submitted
  • 15 October 2025 Planning permission refused

None found. The register holds no published incident that names The Electricity Substation, Baslow Road - Energy Storage System. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.