Onshore wind · United Kingdom

RAF Molesworth Wind Farm

Operator RWE Npower Renewables

Application Refused15 MWData checked 16 November 2026Source record dated 11 December 2014

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

RAF Molesworth Wind Farm is a 15 MW wind farm 6.2 km east of Thrapston, Cambridgeshire, United Kingdom. Its planning application (1200967FUL) went to Huntingdonshire on 18 June 2012 and was refused by the Secretary of State on 5 December 2014. Its status in the Renewable Energy Planning Database (UK government) is application refused. There are 18 other energy sites within 10 km, 4 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 12 other sites and 432 energy sites within 40 km for RAF Molesworth Wind Farm

Members see the sites and incidents around this one, and every record behind them.

Technology
Onshore wind
Capacity
15 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Application Refused (Secretary of State - Refusal)
Operator or applicant
RWE Npower Renewables
Location
sw/o Raf Molesworth, Warren Lane, Bythorn, Huntingdon, Cambridgeshire, Cambridgeshire, PE28 0QU, United Kingdom
Planning authority
Huntingdonshire
Planning application
1200967FUL
Appeal reference
APP/H0520/A/13/2197548
Turbines
6

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 1200967FUL, with what the planning evidence pack adds for this site.

Every application in Huntingdonshire · Alerts for applications and incidents near here

  • 18 June 2012 Planning application submitted
  • 2 May 2014 Planning permission refused
  • 28 June 2014 Appeal lodged
  • 5 December 2014 Refused by the Secretary of State
  • 5 December 2014 Appeal refused

None found. The register holds no published incident that names RAF Molesworth Wind Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has RAF Molesworth Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names RAF Molesworth Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of RAF Molesworth Wind Farm?
Application Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 11 December 2014.
Where is RAF Molesworth Wind Farm?
6.2 km east of Thrapston, Cambridgeshire, United Kingdom (postcode PE28 0QU).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).