Offshore wind · United Kingdom
Race Bank (Phase 2)
Operator Orsted (formerly Dong Energy)& Macquarie Group
Operational284 MWData checked 16 November 2026Source record dated 20 August 2020
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Race Bank (Phase 2) is a 284 MW offshore wind farm 17 km east of Skegness, United Kingdom. Its planning application went to DECC (S36) on 23 January 2009. It has been operating since 1 February 2018. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 5 other energy sites within 10 km. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Race Bank (Phase 2) changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, offshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Offshore wind
- Capacity
- 284 MW (this record)
- All phases
- 573 MW, the phases on the register added up
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- Orsted (formerly Dong Energy)& Macquarie Group
- Location
- Race Bank, Greater Wash, Offshore, United Kingdom
- Planning authority
- DECC (S36)
- First operating
- 2018
- Turbines
- 45, 154 m to tip
This record is 284 MW, one part of a site built in phases. With Race Bank (Phase 1) (290 MW) the phases on the register add up to 573 MW. Race Bank (Phase 1)
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page, with what the planning evidence pack adds for this site.
Every application in DECC (S36) · Alerts for applications and incidents near here
Timeline
- 23 January 2009 Planning application submitted
- 7 July 2016 Construction started
- 1 February 2018 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Race Bank (Phase 2). If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Race Bank (Phase 2) had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Race Bank (Phase 2); it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Race Bank (Phase 2)?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 20 August 2020.
- Where is Race Bank (Phase 2)?
- 17 km east of Skegness, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).