Preston Farm, Preston Candover - Solar PV Array

Awaiting Construction28 MWChecked 6 October 2026Last changed in the dataset 30 January 2024

Technology
Solar
Capacity
28 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
BSR Energy
Location
Preston Candover Church Lane Preston Candover, Hampshire, RG25 2DS, United Kingdom
Planning authority
Basingstoke and Deane
Planning application
21/03398/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 1 November 2021 Planning application submitted
  • 16 September 2022 Planning permission granted
  • 16 September 2027 Planning permission expired

None found. The register holds no published incident that names Preston Farm, Preston Candover - Solar PV Array. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents