← Back to Kent

Battery storage · United Kingdom

Pivot Power Kemsley (Kemsley Substation)

Operator Pivot Power · Owner Pivoted Power LLP

Operational286 MWData checked 11 November 2026Source record dated 9 March 2026

Watch this siteIts outage notices and incidents, what it earns and where it ranks, in your workspace and by email. 7 days free, no card.

Pivot Power Kemsley (Kemsley Substation) is a 286 MW battery storage site on the edge of Sittingbourne, Kent, United Kingdom. Its planning application (19/502514/FULL) went to Swale on 24 May 2019 and was granted on 20 September 2019. It has been operating since 25 October 2021. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 48 other energy sites within 10 km, 12 of them battery storage sites. The register holds no incident at this site. It holds 14 incidents at battery storage sites in the United Kingdom, and 196 worldwide.

The operator's 12 other sites and 440 energy sites within 40 km for Pivot Power Kemsley (Kemsley Substation)

Members see the sites and incidents around this one, and every record behind them.

PIVOT POWER LIMITED (12032042), active, since 2019. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Battery storage (Stand-alone Storage)
Capacity
286 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Pivot Power
Owner
Pivoted Power LLP
Location
Land To The South Of Kemsley S, Ypres Drive, Kemsley, Sittingbourne, Kent, Kent, ME10 2, United Kingdom
Planning authority
Swale
Planning application
19/502514/FULL
First operating
2021

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 19/502514/FULL, with what the planning evidence pack adds for this site.

Every application in Swale · Alerts for applications and incidents near here

  • 24 May 2019 Planning application submitted
  • 20 September 2019 Planning permission granted
  • 15 November 2019 Construction started
  • 25 October 2021 Operational

None found. The register holds no published incident that names Pivot Power Kemsley (Kemsley Substation). If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Pivot Power Kemsley (Kemsley Substation) had a fire or other incident?
None is on the register as of 11 November 2026. The register holds no published incident that names Pivot Power Kemsley (Kemsley Substation); it holds 14 incidents at battery storage sites in the United Kingdom.
What is the status of Pivot Power Kemsley (Kemsley Substation)?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 9 March 2026.
Where is Pivot Power Kemsley (Kemsley Substation)?
On the edge of Sittingbourne, Kent, United Kingdom (postcode ME10 2).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).