← Back to Gwent

Energy sites / United Kingdom / Gwent

Solar · United Kingdom

Newport (Began Road)

Operational4.9 MWChecked 6 October 2026Last changed in the dataset 27 February 2017

Technology
Solar
Capacity
4.9 MW
Status
Operational
Operator or applicant
Eco Energy World
Location
Fairwater Farm, Michaelston-y-Fedw, Gwent, CF3 6XS, United Kingdom
Planning authority
Newport
Planning application
14/0337
First operating
2016

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 3 April 2014 Planning application submitted
  • 22 October 2015 Planning permission granted
  • 14 December 2015 Construction started
  • 14 February 2016 Operational

None found. The register holds no published incident that names Newport (Began Road). If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.