← Back to Kent

Onshore wind · United Kingdom

New Rides Wind Farm

Operator Airvolution Energy · Owner The Government Of Ireland

Operational8.8 MWData checked 16 November 2026Source record dated 29 May 2019

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

New Rides Wind Farm is a 8.8 MW wind farm 8.6 km south-east of Sheerness, Kent, United Kingdom. Its planning application (SW/13/1571) went to Swale on 27 January 2014 and was granted on appeal on 9 August 2017. It has been operating since 1 December 2018. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 45 other energy sites within 10 km, 2 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 29 other sites and 413 energy sites within 40 km for New Rides Wind Farm

Members see the sites and incidents around this one, and every record behind them.

AIRVOLUTION ENERGY LIMITED (07070240), dissolved, since 2009. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
8.8 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Airvolution Energy
Owner
The Government Of Ireland
Location
New Rides Farm, Leysdown Road, Sheerness, Kent, ME12 4DD, United Kingdom
Planning authority
Swale
Planning application
SW/13/1571
Appeal reference
APP/V2255/W/15/3014371
First operating
2018
Turbines
4

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for SW/13/1571, with what the planning evidence pack adds for this site.

Every application in Swale · Alerts for applications and incidents near here

  • 27 January 2014 Planning application submitted
  • 3 February 2015 Planning permission refused
  • 25 June 2015 Appeal lodged
  • 9 August 2017 Planning permission granted
  • 9 August 2017 Appeal granted
  • 7 June 2018 Construction started
  • 1 December 2018 Operational

None found. The register holds no published incident that names New Rides Wind Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has New Rides Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names New Rides Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of New Rides Wind Farm?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 29 May 2019.
Where is New Rides Wind Farm?
8.6 km south-east of Sheerness, Kent, United Kingdom (postcode ME12 4DD).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).