← Back to Cheshire

Energy sites / United Kingdom / Cheshire

Battery storage · United Kingdom

Native River

Operational57 MWChecked 6 October 2026Last changed in the dataset 28 April 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
57 MW
Status
Operational
Operator or applicant
Varco Energy
Location
Adj Electricity Substation, Cheshire, CH66 2HD, United Kingdom
Planning authority
Cheshire West and Chester
Planning application
20/04767/FUL
First operating
2025

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 17 December 2020 Planning application submitted
  • 16 April 2021 Planning permission granted
  • 1 July 2023 Construction started
  • 14 April 2025 Operational

None found. The register holds no published incident that names Native River. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.