← Back to Cheshire

Energy sites / United Kingdom / Cheshire

Battery storage · United Kingdom

Capenhurst Lane, Capenhurst - Battery Storage

Awaiting Construction100 MWChecked 6 October 2026Last changed in the dataset 13 December 2023

Technology
Battery storage (Stand-alone Storage)
Capacity
100 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Aura Power BESS Limited
Location
South of Capenhurst Lane Capenhurst, Cheshire, CH66 2NT, United Kingdom
Planning authority
Cheshire West and Chester
Planning application
22/03585/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 22 September 2022 Planning application submitted
  • 8 December 2023 Planning permission granted
  • 8 December 2026 Planning permission expired

None found. The register holds no published incident that names Capenhurst Lane, Capenhurst - Battery Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.