Capenhurst Lane, Capenhurst - Battery storage

Under Construction57 MWChecked 6 October 2026Last changed in the dataset 15 September 2022

Technology
Battery storage (Stand-alone Storage)
Capacity
57 MW
Status
Under Construction
Operator or applicant
HD888CAP Limited
Location
Capenhurst Lane Capenhurst Chester, Cheshire, CH1 6EH, United Kingdom
Planning authority
Cheshire West and Chester
Planning application
21/02404/FUL

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 3 June 2021 Planning application submitted
  • 11 March 2022 Planning permission granted
  • 1 September 2022 Construction started
  • 21 October 2024 Planning permission expired

None found. The register holds no published incident that names Capenhurst Lane, Capenhurst - Battery storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents