Application Refused8 MWData checked 16 November 2026Source record dated 9 May 2006

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Hill of Lieurary is a 8 MW wind farm 7.3 km south of Thurso, Highland, United Kingdom. Its planning application (CA2003323) went to Highland on 10 July 2003 and was refused on 16 September 2005. Its status in the Renewable Energy Planning Database (UK government) is application refused. There are 25 other energy sites within 10 km, 11 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

130 energy sites within 40 km for Hill of Lieurary

Members see the sites and incidents around this one, and every record behind them.

Technology
Onshore wind
Capacity
8 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Application Refused (Planning Permission Refused)
Operator or applicant
Scotrenewables
Location
Hill of LieuraryWestfieldThursoCaithness, Highland, United Kingdom
Planning authority
Highland
Planning application
CA2003323
Appeal reference
P/PPA/270/369
Turbines
3

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for CA2003323, with what the planning evidence pack adds for this site.

Every application in Highland · Alerts for applications and incidents near here

  • 10 July 2003 Planning application submitted
  • 16 September 2005 Planning permission refused

None found. The register holds no published incident that names Hill of Lieurary. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Hill of Lieurary had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Hill of Lieurary; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Hill of Lieurary?
Application Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 9 May 2006.
Where is Hill of Lieurary?
7.3 km south of Thurso, Highland, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).