Glengolly Farmhouse- Battery Energy Storage

Awaiting Construction49.9 MWChecked 6 October 2026Last changed in the dataset 4 November 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Ecocel Energy Storage Limited
Location
Land 500M East Of Glengolly Farmhouse Thurso, Highland, KW14 7XH, United Kingdom
Planning authority
Highland
Planning application
24/00561/FUL
  • 6 March 2024 Planning application submitted
  • 1 April 2025 Planning permission refused
  • 30 September 2025 Appeal granted
  • 30 September 2028 Planning permission expired

None found. The register holds no published incident that names Glengolly Farmhouse- Battery Energy Storage. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.