Solar · United Kingdom
Glebe Farm Solar Farm
Operational32 MWChecked 6 October 2026Last changed in the dataset 3 September 2020
The site
- Technology
- Solar
- Capacity
- 32 MW
- Status
- Operational
- Operator or applicant
- NextEnergy Capital LLP
- Location
- Glebe Farm, Bourne Road, Defford, Worcester, Hereford and Worcester, WR8 9BT, United Kingdom
- Planning authority
- Wychavon
- Planning application
- 15/01323
- First operating
- 2021
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 21 May 2015 Planning application submitted
- 21 October 2015 Planning permission granted
- 1 June 2020 Construction started
- 1 March 2021 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Glebe Farm Solar Farm. If you know of one, report it (confidential reports are anonymised).
Follow Glebe Farm Solar Farm
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at solar farms in the United Kingdom
The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.
- Fire involving solar panels at a Market Harborough house spreads to an adjoining property
- Solar inverter fire on agricultural building in Shropshire
- Fire damages solar panel batteries in a Teignmouth garage
- Fire damages roof with one solar panel in The Charltons
- Solar panels on flat roof alight at terraced building in Newquay
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.