Four Burrows Solar farm

Operator TRIG

Operational7.2 MWData checked 16 November 2026Source record dated 30 March 2015

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Four Burrows Solar farm is a 7.2 MW solar farm 7.5 km north-west of Truro, Cornwall, United Kingdom. Its planning application (PA10/07942) went to Cornwall on 2 December 2010 and was granted on 3 March 2011. It has been operating since 12 January 2015. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 35 other energy sites within 10 km, 23 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

183 energy sites within 40 km for Four Burrows Solar farm

Members see the sites and incidents around this one, and every record behind them.

Technology
Solar
Capacity
7.2 MW (this record)
All phases
15 MW, the phases on the register added up
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
TRIG
Location
Little Lambriggan Penhallow Truro Cornwall, Cornwall, TR4 9NG, United Kingdom
Planning authority
Cornwall
Planning application
PA10/07942
First operating
2015

This record is 7.2 MW, one part of a site built in phases. With Four Burrows Farm (Extension 2) (6.3 MW), Four Burrows Solar farm (Extension 1) (1.5 MW) the phases on the register add up to 15 MW. Four Burrows Farm (Extension 2) · Four Burrows Solar farm (Extension 1)

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for PA10/07942, with what the planning evidence pack adds for this site.

Every application in Cornwall · Alerts for applications and incidents near here

  • 2 December 2010 Planning application submitted
  • 3 March 2011 Planning permission granted
  • 1 July 2014 Construction started
  • 12 January 2015 Operational

None found. The register holds no published incident that names Four Burrows Solar farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Four Burrows Solar farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Four Burrows Solar farm; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Four Burrows Solar farm?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 30 March 2015.
Where is Four Burrows Solar farm?
7.5 km north-west of Truro, Cornwall, United Kingdom (postcode TR4 9NG).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).