Cwm Derwyn Farm

Operational5 MWChecked 6 October 2026Last changed in the dataset 24 March 2017

Technology
Solar
Capacity
5 MW
Status
Operational
Operator or applicant
Kronos Solar
Location
Cwm Derwyn Farm, Waycock Road, Barry, South Glamorgan, Vale of Glamorgan, CF62 3AA, United Kingdom
Planning authority
Vale of Glamorgan
Planning application
2015/00632/FUL
First operating
2017

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 1 June 2015 Planning application submitted
  • 4 September 2015 Planning permission granted
  • 15 January 2017 Construction started
  • 17 March 2017 Operational

None found. The register holds no published incident that names Cwm Derwyn Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.