← Back to Highland

Onshore wind · United Kingdom

Coire Na Cloiche Wind Farm

Operator RockbySea

Operational29.9 MWData checked 16 November 2026Source record dated 23 March 2020

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Coire Na Cloiche Wind Farm is a 29.9 MW wind farm 11 km north-west of Alness, Highland, United Kingdom. Its planning application (12/00479/FUL) went to Highland on 16 February 2012 and was granted on 25 April 2013. It has been operating since 1 March 2020. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 15 other energy sites within 10 km, 8 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

117 energy sites within 40 km for Coire Na Cloiche Wind Farm

Members see the sites and incidents around this one, and every record behind them.

7 Oct25 Oct
WholesaleBalancing mechanism

Full revenue and market view The pounds behind each bar, any period back to 2021, where it ranks against every site like it, who trades it, and a side-by-side with any other site.

29 settled days to 4 Nov: 626 MWh, running 22% of half hours, peak 11 MW of 30, load factor 3%. Members see what that output was worth at the market index price, half hour by half hour, and the rate per MW a year.

A day out costs this site about £2,233 at its earnings over the last 29 settled days (wholesale at the market index price). A figure from the market, not a claim: what the site earned, averaged, is what a day out forgoes.

Contains BMRS data © Elexon Limited copyright and database right (datasets B1610 and MID, the interim settlement run). Read each morning; a settled figure can be revised in later runs.

Technology
Onshore wind
Capacity
29.9 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
RockbySea
Location
Land At Sidhean A'Choin Bhain, Strathrusdale, Alness, Highland, IV17 0YQ, United Kingdom
Planning authority
Highland
Planning application
12/00479/FUL
First operating
2020
Turbines
13

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 12/00479/FUL, with what the planning evidence pack adds for this site.

Every application in Highland · Alerts for applications and incidents near here

  • 16 February 2012 Planning application submitted
  • 25 April 2013 Planning permission granted
  • 24 August 2017 Construction started
  • 1 March 2020 Operational

None found. The register holds no published incident that names Coire Na Cloiche Wind Farm. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Coire Na Cloiche Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Coire Na Cloiche Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Coire Na Cloiche Wind Farm?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 23 March 2020.
Where is Coire Na Cloiche Wind Farm?
11 km north-west of Alness, Highland, United Kingdom (postcode IV17 0YQ).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).