← Back to Lancashire

Energy sites / United Kingdom / Lancashire

Battery storage · United Kingdom

Clifton Marsh Waste Water Treatment Works

Operational2 MWChecked 6 October 2026Last changed in the dataset 1 June 2020

Technology
Battery storage (Co-located with RE)
Capacity
2 MW
Status
Operational
Operator or applicant
United Utilities
Location
CLIFTON MARSH WASTE WATER TREATMENT WORKS, PRESTON NEW ROAD, FRECKLETON, Lancashire, United Kingdom
Planning authority
Fylde
Planning application
LCC/2019/0045
First operating
2020

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 1 August 2019 Planning application submitted
  • 28 August 2019 Planning permission granted
  • 1 February 2020 Construction started
  • 1 June 2020 Operational

None found. The register holds no published incident that names Clifton Marsh Waste Water Treatment Works. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.