Clay Tye Farm Phase 1 - Storage Facility

Operational49.5 MWChecked 6 October 2026Last changed in the dataset 27 March 2024

Technology
Battery storage (Stand-alone Storage)
Capacity
49.5 MW
Status
Operational
Operator or applicant
Harmony Energy Storage
Location
Clay Tye Farm, Clay Tye Road, Upminster, London, RM14 3PL, United Kingdom
Planning authority
Havering
Planning application
P0611.17
First operating
2024

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 28 April 2017 Planning application submitted
  • 18 July 2017 Planning permission refused
  • 1 July 2022 Construction started
  • 6 March 2023 Planning permission granted
  • 22 March 2024 Operational

None found. The register holds no published incident that names Clay Tye Farm Phase 1 - Storage Facility. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents