← Back to North Yorkshire

Energy sites / United Kingdom / North Yorkshire

Onshore wind · United Kingdom

Chelker Reservoir Repower (Resubmission)

Application Refused1.7 MWChecked 6 October 2026Last changed in the dataset 29 March 2012

Technology
Onshore wind
Capacity
1.7 MW
Status
Application Refused (Planning Permission Refused)
Operator or applicant
Kelda Water Services
Location
Chelker Reservoir, Addingham, Ilkley, West Yorkshire, North Yorkshire, United Kingdom
Planning authority
North Yorkshire
Planning application
24/2011/12076
Turbines
2

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 7 October 2011 Planning application submitted
  • 13 March 2012 Planning permission refused

None found. The register holds no published incident that names Chelker Reservoir Repower (Resubmission). If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.