← Back to Humberside

Energy sites / United Kingdom / Humberside

Onshore wind · United Kingdom

Celcon Blocks Ltd

Operational2 MWChecked 6 October 2026Last changed in the dataset 21 February 2017

Technology
Onshore wind
Capacity
2 MW
Status
Operational
Operator or applicant
Ecotricity / Next Generation
Location
Heck and Pollington Lane, Pollington, Goole, Humbs, Humberside, DN14 0BA, United Kingdom
Planning authority
East Riding of Yorkshire
Planning application
09/02681/STPLF
Appeal reference
12/00045/REFUSE
First operating
2016
Turbines
1

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 4 August 2009 Planning application submitted
  • 18 May 2012 Appeal lodged
  • 17 October 2012 Planning permission granted
  • 17 October 2012 Appeal granted
  • 15 April 2015 Construction started
  • 15 April 2016 Operational
  • 27 April 2018 Planning permission refused

None found. The register holds no published incident that names Celcon Blocks Ltd. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.