Cairnmore Farm

Operational2.6 MWChecked 6 October 2026Last changed in the dataset 6 August 2010

Technology
Onshore wind
Capacity
2.6 MW
Status
Operational
Operator or applicant
Private Developer
Location
3km south-east of Rhynie in Aberdeenshire, Grampian, United Kingdom
Planning authority
Aberdeenshire
Planning application
APP/2008/1486
First operating
2010
Turbines
3

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 18 April 2008 Planning application submitted
  • 27 October 2009 Planning permission granted
  • 1 April 2010 Construction started
  • 10 July 2010 Operational

None found. The register holds no published incident that names Cairnmore Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.