← Back to Clackmannanshire

Energy sites / United Kingdom / Clackmannanshire

Onshore wind · United Kingdom

Burnfoot Hill

Operational26 MWChecked 6 October 2026Last changed in the dataset 3 November 2010

Technology
Onshore wind
Capacity
26 MW
Status
Operational
Operator or applicant
EDF Energies Nouvelles
Location
Burnfoot Hill, Clackmannanshire, Clackmannanshire, United Kingdom
Planning authority
Clackmannanshire
Planning application
06/00121/FULL
First operating
2010
Turbines
13

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 20 March 2006 Planning application submitted
  • 28 March 2007 Planning permission granted
  • 1 August 2010 Construction started
  • 26 October 2010 Operational

None found. The register holds no published incident that names Burnfoot Hill. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.