← Back to Lincolnshire

Energy sites / United Kingdom / Lincolnshire

Solar · United Kingdom

Belvoir Estate - Solar farm

Awaiting Construction49.9 MWChecked 6 October 2026Last changed in the dataset 10 February 2026

Technology
Solar
Capacity
49.9 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
JBM Solar Projects Limited
Location
Land To The South West Of Easthorpe Lane Muston, Lincolnshire, NG32 1PE, United Kingdom
Planning authority
Melton
Planning application
22/00537/FUL
Appeal reference
APP/Y2430/W/24/3340258

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 1 April 2022 Planning application submitted
  • 11 September 2023 Planning permission refused
  • 7 March 2024 Appeal lodged
  • 25 February 2025 Appeal granted
  • 25 February 2028 Planning permission expired

None found. The register holds no published incident that names Belvoir Estate - Solar farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.