Solar · United Kingdom
Belvoir Fruit Farms, Barkestone Lane - Solar Panels
Operator Watt Energy Saver Limited
Awaiting Construction0.2 MWData checked 16 November 2026Source record dated 26 January 2026
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Belvoir Fruit Farms, Barkestone Lane - Solar Panels is a 0.2 MW solar farm 9.9 km east of Bingham, Nottinghamshire, United Kingdom. Its planning application (25/01068/GDOPV) went to Melton on 9 October 2025 and was granted on 2 December 2025. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 24 other energy sites within 10 km, 19 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.
Get an email when Belvoir Fruit Farms, Barkestone Lane - Solar Panels changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, solar PV incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every solar incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Belvoir Fruit Farms, Barkestone Lane - Solar Panels sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.
Get the evidence pack for this site, £295 See a sample pack (PDF)
Preview of the planning evidence pack for this site
The pack for this site lists 104 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1265, Solar panels catch fire and destroy three buildings in Harby, 8.2 km from this site.
| Reference | Year | Incident | From the site | Severity |
|---|---|---|---|---|
| EIR-1265 | 2024 | Solar panels catch fire and destroy three buildings in Harby | 8.2 km | Significant |
| EIR-0764 | 2024 | Transformer smoking at solar farm in Burton Pedwardine | 32 km | Minor |
| EIR-2151 | 2018 | Sunlight reflected from a shed solar panel believed to have started a house fire in Thurnby Lodge | 36 km | Significant |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
| •••••••• | •••• | •••••••••••••••••••••••••••••• | •••• | •••••• |
The first 3 rows as the pack shows them. The other 101 are in the pack, each with its distance, sources and the fire service guidance it bears on.
The map
Summary for this site
This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.
Paragraphs for the planning statement
This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.
In the full packThe site
- Technology
- Solar
- Capacity
- 0.2 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Awaiting Construction (Planning Permission Granted)
- Operator or applicant
- Watt Energy Saver Limited
- Location
- Belvoir Fruit Farms, Barkestone Lane, Bottesford, Nottingham, Nottinghamshire, NG13 0DH, United Kingdom
- Planning authority
- Melton
- Planning application
- 25/01068/GDOPV
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 25/01068/GDOPV, with what the planning evidence pack adds for this site.
Every application in Melton · Alerts for applications and incidents near here
Timeline
- 9 October 2025 Planning application submitted
- 2 December 2025 Planning permission granted
Incidents on the register at this site
None found. The register holds no published incident that names Belvoir Fruit Farms, Barkestone Lane - Solar Panels. If you know of one, report it (confidential reports are anonymised).
Questions
- Has Belvoir Fruit Farms, Barkestone Lane - Solar Panels had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Belvoir Fruit Farms, Barkestone Lane - Solar Panels; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
- What is the status of Belvoir Fruit Farms, Barkestone Lane - Solar Panels?
- Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 26 January 2026.
- Where is Belvoir Fruit Farms, Barkestone Lane - Solar Panels?
- 9.9 km east of Bingham, Nottinghamshire, United Kingdom (postcode NG13 0DH).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).