Onshore wind · United Kingdom
Altamuskin Extension
Operator Altamuskin Windfarm (Energia)
Operational7.1 MWData checked 16 November 2026Source record dated 4 May 2017
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Altamuskin Extension is a 7.1 MW wind farm 16 km south-east of Omagh, Co. Tyrone, United Kingdom. Its planning application (K/2011/0239/F) went to Fermanagh and Omagh on 13 April 2011 and was granted on 28 January 2015. It has been operating since 15 March 2017. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 24 other energy sites within 10 km, 19 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Altamuskin Extension changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 7.1 MW (this record)
- All phases
- 14.2 MW, the phases on the register added up
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- Altamuskin Windfarm (Energia)
- Location
- Sixmilecross, Clogher, Co. Tyrone, Co. Tyrone, United Kingdom
- Planning authority
- Fermanagh and Omagh
- Planning application
- K/2011/0239/F
- First operating
- 2017
- Turbines
- 3, 110 m to tip
This record is 7.1 MW, one part of a site built in phases. With Altamuskin (7.1 MW) the phases on the register add up to 14.2 MW. Altamuskin
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for K/2011/0239/F, with what the planning evidence pack adds for this site.
Every application in Fermanagh and Omagh · Alerts for applications and incidents near here
Timeline
- 13 April 2011 Planning application submitted
- 28 January 2015 Planning permission granted
- 1 March 2016 Construction started
- 15 March 2017 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Altamuskin Extension. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Altamuskin Extension had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Altamuskin Extension; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Altamuskin Extension?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 4 May 2017.
- Where is Altamuskin Extension?
- 16 km south-east of Omagh, Co. Tyrone, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).