← Back to Strathclyde

Onshore wind · United Kingdom

A'Chruach (Phase 1)

Operator Infinis (formerly Novera Energy)

Operational48.3 MWData checked 16 November 2026Source record dated 4 April 2017

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

A'Chruach (Phase 1) is a 48.3 MW wind farm 31 km south of Oban, Strathclyde, United Kingdom. Its planning application (11/02520/PP) went to Argyll and Bute on 22 December 2011 and was granted on 27 June 2012. It has been operating since 29 June 2016. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 4 other energy sites within 10 km, 3 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 1 other site and 64 energy sites within 40 km for A'Chruach (Phase 1)

Members see the sites and incidents around this one, and every record behind them.

Technology
Onshore wind
Capacity
48.3 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Infinis (formerly Novera Energy)
Location
Land At A'CruachKilmichael ForestWest Of MinardArgyll, Strathclyde, United Kingdom
Planning authority
Argyll and Bute
Planning application
11/02520/PP
First operating
2016
Turbines
21

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 11/02520/PP, with what the planning evidence pack adds for this site.

Every application in Argyll and Bute · Alerts for applications and incidents near here

  • 22 December 2011 Planning application submitted
  • 27 June 2012 Planning permission granted
  • 4 June 2015 Construction started
  • 29 June 2016 Operational

None found. The register holds no published incident that names A'Chruach (Phase 1). If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has A'Chruach (Phase 1) had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names A'Chruach (Phase 1); it holds 63 incidents at wind farms in the United Kingdom.
What is the status of A'Chruach (Phase 1)?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 4 April 2017.
Where is A'Chruach (Phase 1)?
31 km south of Oban, Strathclyde, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).